Westfield Road Construction Schedule Announced
The City of Westfield is pleased to provide the following anticipate schedule for its 2025 road construction season. These projects include new roundabouts and improvements to the city’s trail network.
“My administration is focused on improving our infrastructure and projects like these are vital to our community,” stated Mayor Scott Willis. “The construction season has a limited window in Indiana, and there will be record investment in much needed improvement projects occurring this summer. Please be patient as we navigate through the city.”
Roadway Projects
151st St & Towne Rd Roundabout (80 days*)
Full closure; projected to start no later than April 7
2025 Concrete Patching (Bridlewood Subdivision)
No Closure; Start Date: by mid-April, completed by May 30
161st St & Spring Mill Rd Roundabout (60 days*)
Full closure; projected to start May 1; project includes pedestrian bridge over John Edwards Drain
181st St & Wheeler Rd Roundabout (45 days*)
Full closure; projected to start May 27
Old 146th St & Towne Rd Roundabout
2 phase closure; Summer 2025
171st St & Ditch Rd Roundabout
Summer 2025
Mule Barn Road Widening
Fall 2025
Trail Projects
Monon Tunnel
161st Street will remain open to traffic; Monon Trail will have a detour; Summer 2025
161st St Trail (Oak Rd to Carey Rd)
No closure; Summer/Fall 2025
151st St Trail (Oak Rd to Bridlewood Subdivision)
Fall 2025
More detailed information, including detour routes and project costs, can be found at westfieldin.gov/construction. The City of Westfield will also post frequent updates on Facebook.
*All dates are estimates. Weather, utilities and unforeseen circumstances may impact the schedule.