Westfield Announces Construction, Repaving Schedule

The City of Westfield Public Works Department has announced this year’s road construction and street repaving projects. 

“Over the past two years, Westfield has made record investments on infrastructure to ensure our roadways keep pace with our growth,” said Mayor Scott Willis. “These projects are about getting our roads right-sized, improving safety and connectivity, and continuing to close trail gaps so residents can move throughout our city more easily.”

181st Street and Grand Park Boulevard: begins April 4, 2026
Roundabout construction; anticipated closure for 60 days

191st Street Widening: Utility Work this Spring; Roundabout construction this fall
Widening of 191st Street from Tomlinson Road to Grand Park Boulevard, including a roundabout at Grand Park Boulevard and a pedestrian bridge for Monon over 191st. Remaining construction on 191st Street and the Monon pedestrian bridge over 191st is projected for Spring 2027.

State Road 32: through end of 2026
Road widening work on the south side of State Road 32 will begin this Spring, along with construction of the SR 32 & East Street roundabout. Traffic will remain open east-west during construction. Later in the year, traffic will be shifted south on the newly constructed roadway to allow the contractor to complete the remaining north side reconstruction work. All construction work is anticipated to be completed by the end of the year.

Monon Tunnel: through end of 2026
Work on the Monon Tunnel at 161st Street began March 2, 2026. Work will continue through the end of the year. While a full closure of 161st Street is not anticipated, there could be lane restrictions at times.

Penn Street Extension: August 2026
The Penn Street extension is a new roadway segment to connect Penn Street from East Street to Hillcrest Drive, just north of the Ambrose on Main project. The project will include on-street parking, sidewalks, lighting, and signage; anticipated closure for 60 days.

Additional projects include a traffic signal at Grand Park Boulevard and Tournament Trail, widening of Mule Barn Road, downtown drainage improvements, and a raised crosswalk at 151st Street and American Lotus Drive. For a full list of projects, visit westfieldin.gov/construction.

Repaving Projects
Street repaving projects will begin approximately the first week of May and continue through the first week of October. More firm timelines will be announced as the summer progresses.

Each paving project begins with milling the top surface of asphalt and repaving it with a new layer about two to four inches thick. Typical milling and paving projects take three to five days to complete and require lane restrictions. 
 

VILLAGE FARMS
 
Street NameFromTo
Kings Point CourtSenator WayTerminus
Senator WayW Greyhound PassKings Point Court
Fox CourtSenator WayTerminus
Abbedale CourtSenator WayTerminus
Pacer CourtAbbedale CourtTerminus
Trotter CourtAbbedale CourtTerminus
Roman CourtW. Greyhound PassTerminus
Admiral Way NW. Senator WayW Laredo Way S
Admiral Way SAdmiral Way NAdios Pass
Alsong CourtAdmiral Way STerminus
Shower CourtAdmiral Way STerminus
Laredo Way SAdmiral Way NAmkey Way
Laredo Way NAmkey WaySulky Way
Laredo CourtLaredo Way STerminus
Amkey WaySenator WayTerminus
Amkey CourtAmkey WayTerminus
Mercury CourtLaredo Way NTerminus
Sulky WayLaredo Way SSenator Way
Derby CourtW. Greyhound PassTerminus
Senator WayAmkey WayTerminus
OAK MANOR
 
Street NameFromTo
Chalet CircleOak Manor DriveTerminus
Cyprian CircleDaylily CourtTerminus
Daylily CourtOak Manor DriveTerminus
Oak Manor DriveOak Road 275′ EDaylily Court 190′ N
COUNTRYSIDE
 
Street NameFromTo
E Clear Lake LaneKirklin DriveGrabill Drive
Grabill DriveKirklin DriveVernon Place
Vernon PlaceKirklin DriveTerminus
Kirklin DriveE Clear Lake LaneVernon Place
E Quail Ridge DriveVernon PlaceVernon Place 160′ N
OAK PARK
 
Street NameFromTo 
Oak Park Court161st StreetTerminus 
Oak Park CircleOak Park CourtOak Park Court 650′ E 
HILLCREST
 
Street NameFromTo
Hillcrest DriveSR 32SR 32
THOROUGHFARES
 
Street NameFromTo 
Western Way146th StreetGreyhound Pass 
Greyhound PassUS 31 CDWestern Way 115′ N 
Wheeler Road181st Street 300′ N186th Street 
186th StreetWheeler RoadGrand Park Blvd 340′ E 
Grand Park Blvd186th Street 325′ S186th Street 950′ S 
156th StreetSpring Mill Road 745′ EOak Ridge Road 
156th StreetEdenvale Drive 300′ WKingsway Ct 225′ E 
Towne RoadKimblewick Blvd 360′ N156th Street 150′ S 
Oak Road161st Street 300′ S151st Street 
196th StreetGrassy Branch RoadMoontown Road 
Eagletown Road166th StreetSR 32 
Ditch RoadSomerville Drive156th Street 

The Indiana Department of Transportation (INDOT) awarded Westfield an additional $911,000 through the Community Crossings Matching Grant (CCMG) program following bid openings for repaving projects. More repaving projects will be announced at a later date.

For a full list of projects, visit westfieldin.gov/construction.